← Sunday, November 15 deck

13Infrastructure1 source posting

Zerohedge: Blackstone's QTS Raises Only $300 Million of an $800 Million Data Center Debt Sale

First Junk, Now Investment Grade: Blackstone's Own Data Center Giant Can't Sell $800 Million Of Debt

Context

Why it matters

When an investment grade data center operator backed by Blackstone cannot sell all of its debt at its price, it signals that lenders are getting choosier about financing the AI buildout.

Bloomberg first reported on November 14 that QTS was cutting a private debt sale by about 60 percent. Zerohedge's post on the evening of November 15 framed it as part of a wider strain in AI data center credit. Blackstone bought QTS in 2021 for about $10 billion including debt.

Deep dive

According to Bloomberg, as published by The Business Times, QTS is raising about $300 million after first targeting roughly $800 million in the private placement market, because it struggled to attract enough investor demand and refused to pay much higher yields. Some investors balked at the price, and others were limited because QTS has tapped the private placement market several times, the report said, citing people familiar with the deal.

The smaller financing includes a $100 million seven year private placement priced on Friday at 2.45 percentage points over benchmarks, plus a $200 million five year bank loan to be priced in the coming weeks. Blackstone chose to proceed at its preferred pricing instead of raising spreads for the full amount, partly because wider pricing could set a more expensive reference point for other Blackstone related debt. QTS had planned to use the money to refinance existing bank debt, which can now stay in place.

Zerohedge headlined the episode First Junk, Now Investment Grade, arguing that strain has spread from riskier AI borrowers to high grade ones, and posted that the data center debt pipeline is full. QTS has still raised large sums this year, including project finance green bonds of $4.6 billion in April and $3.9 billion in August. On the same day, the FT reported that data center construction stocks had lost $4.2 trillion as the boom in the AI trade unravels.

What to expect next

Watch upcoming AI infrastructure debt deals for wider spreads or smaller sizes, especially in private placements, where long term investors such as life insurers limit how much they lend to one borrower. Nvidia's results on November 17 and any change in its credit guarantees will also shape lenders' appetite. If more issuers follow QTS and shrink their deals, the cost of building AI data centers will rise.